The accessibility of Port of Antwerp-Bruges is important for the companies, customers and people who work there. In various parts of the port area we are working to improve the infrastructure for vehicle and cycle traffic. This causes temporary inconvenience from time to time. View the overview of all road works.
Roadworks in Antwerp
In collaboration with Lantis and the Roads and Traffic Agency, we provide an overview of the construction sites that have the most impact on road traffic in and around the Antwerp port area. In this regard, we endeavour to keep the port as accessible as possible for all users, also during the works on the Oosterweel link.
Downloads
More information on the works on the map
1. N101 Scheldelaan: Boudewijn bridge - more information
2. N101 Scheldelaan - Kastelweg - more information
3. Royers lock: renovation
4. N101 Scheldelaan: Zandvlietbrug - more information
5. Oosterweel junction - more information
6. N101 Scheldelaan: high-voltage cables - more information
7. R1 bypass construction - more information
8. R2: maintenance/renovation Beveren tunnel - more information
9. N180 Noorderlaan: construction of heat network - more information
10. N101 Scheldelaan: Oudendijkbrug - more information
N101 Scheldelaan: Replacement of the Boudewijn bridge
Project
The Boudewijn bridge will be replaced by a new bridge. Disruption is expected until end of 2025.
Disruption
If the Meestoof bridge is raised, freight traffic (+3.5t) has to wait; other traffic can drive over the lock gate.
N101 Various works near Zandvliet and Berendrecht Lock
The next few years many works are planned on and around the Zandvliet-Berendrecht lock complex, including maintenance work on the road surface, on bridges, on the Berendrecht lock, works for safer cycling infrastructure, the construction of a new ACC between the locks, the renovation of the Europa terminal, a high-voltage power line along Scheldelaan, works on the public lighting on Scheldelaan,...
There are no ongoing works.
Bike path Scheldelaan (N101)
Project: Fluxys is laying CO2 and H2 pipelines. The works site runs from the intersection with Polderdijkweg to the Boudewijn-Van Cauwelaert lock complex and from Boudewijn Lock to Lillo.
Period: 12 May until the end of 2025.
Hindrance: The cycle path will not be available. Cyclists use the tow path on top of the Scheldedijk.
Scheldelaan (N101) North of R2
Project: water-link lays a cooling water pipeline on the Scheldelaan between the Liefkenshoek Tunnel and the site of Ineos.
Works run from 12 May 2025 -20 December
More info on water-link's website.
Tijsmans Tunnel (R2)
Since 11 May, Agentschap Wegen en Verkeer (AWV) renews the lighting in the Tijsmans Tunnel towards A12/Netherlands.
AWV works every evening from Sunday to Thursday, each time from 8 pm to 5 am the following morning.
During the works, the Tijsmans Tunnel towards A12/Netherlands will be closed.
Traffic from the E34 (West) and E17 towards the A12/Netherlands will divert via the Kennedy Tunnel (R1).
Local traffic will divert via the Scheldelaan (N101) and the Noordland Bridge.
All information on dates and diversions can be found on the AWV website.
Attention: the tunnel in the direction of Ghent is closed for urgent repairs from Friday 13 June 10pm until Monday 16 June 5am.
Oosterweelsteenweg
Lantis works on the Oosterweelsteenweg during three weekends.
From Saturday, July 5 (6 a.m.) to Sunday, July 6 (9 p.m.) and from Saturday, July 12 (6 a.m.) to Sunday, July 13 (9 p.m.), the Oosterweelsteenweg will be closed for traffic in the direction of the port. Detour via Vosseschijnstraat/Noordkasteelbrug.
Cyclists can pass the works in both directions.
From Saturday, August 2 (6 a.m.) to Sunday, August 3 (9 p.m.) Oosterweelsteenweg will be closed to car traffic in both directions. Detour via Vosseschijnstraat/Noordkasteelbrug.
Cyclists can pass the works in both directions.
All info on the Lantis website.
Sint-Antoniusweg
Project: Unscheduled works on St Antonius Road due to a collapsed sewer cover at the roundabout.
Period: from 11 July in the morning until 15 July in the evening
Mexico bridge breakdown
Since 21 June, the Mexico bridges have been open due to a defect. As a result, the bridges are inaccessible to all road traffic.
These bridges are not managed by the Antwerp Port Authority, but by the City of Antwerp. For the latest information, please visit the Slim naar Antwerpen website (in Dutch).
Periodic maintenance tunnels
Project
For Liefkenshoek Tunnel the dates of maintenance works are published on the Liefkenshoek Tunnel website.
For other tunnels the dates can be found on the website of Vlaams Verkeerscentrum.
Lillo bridge not available
Lillo bridge is not available for trains, road transport and cyclists.
Cyclists can use the “bike bus” to cross the Kanaaldok.
More info on the roadworks in Antwerp
Slim naar Antwerpen
for road works in the city of Antwerp
Roads and Traffic Agency
for the latest information on their roadworks in the Antwerp port area
Lantis
for the latest news about the works on the Oosterweel link
Roadworks in Zeebrugge
Herdersbrug (N348)
Project: The Flemish Maritime Access Agency (AMT) carries out maintenance works on the Herders Bridge (Herdersbrug)
Period: phase 1 is finished; final phase is planned from 27 Juni until 5 July
Hindrance: The Herders Bridge is closed to all road traffic.
Through traffic follows a diversion via the A11, local traffic drives via Lodewijk Coiseaukaai and Pathoekeweg.
Verbindings Bridge interrupted
Project: From mid-May, Lantis will transport the sections of the Scheldt Tunnel from Zeebrugge to Antwerp. The tunnel elements will sail past the Verbindings Bridge. During these moments, no traffic is possible on the Verbindings Bridge.
Period: 8 times between mid-May and the end of August
Hindrance: All traffic, including cyclists, must detour.
All info on the website of the Oosterweelverbinding where you can also register to receive an e-mail with the latest on the interruption.