Request for Proposal: Strategic partner in large-scale BESS-projects

Port of Antwerp-Bruges (POAB) is taking the lead in the energy transition and is further investing in the expansion of its sustainable energy infrastructure.

Strategic and financial partnership

For this reason, POAB wishes to develop Battery Energy Storage Systems (BESS) in the Port of Antwerp, which will play a crucial role in the stability of the electricity grid. POAB is therefore seeking a strategic and financial partner for a new Special Purpose Vehicle (SPV), with a participation of up to 49%, to jointly realize this sustainable energy infrastructure on two sites in the port.

Who is this survey intended for?

POAB invites investors and operators with demonstrable expertise and measurable expertise in large-scale energy projects. To be considered as a partner, you must have the following:

 

  • At least one operational battery storage system that is already connected to the Elia transmission grid.
  • Or a confirmed commitment for future BESS installations on the Elia grid, evidenced by a final investment decision (FID) and/or a signed connection contract.

POAB is making two sites available through a domain concession for the SPV to be established:

Site 1: NextGen District (Right Bank)

  • Location: Situated in the NextGen District, within a 200-meter radius of the new Elia substation Churchilldok.
  • Area: Site of approximately 10,000m2, a portion of which will be reserved for the construction and operation of a substation for distribution system operator Fluvius.
  • Capacity: Estimated storage capacity of 100 MW - 400 MWh.

Site 2: Hazopweg (Left Bank)

  • Location: Situated on the left bank, opposite the intersection of Hazopweg and Land van Waasland to Beveren-Kruibeke-Zwijndrecht.
  • Area: Site of approximately 6,626m2.
  • Capacity: Estimated storage capacity of 35 MW -  140 MWh

How to participate?

Submit your vision and proposal via the button below, including:

  • response form
  • requested documentation
  • appendix 1

The deadline for your application is Friday, January 16, 2026, at 4:00 PM.

Submit project proposal

Request for project proposals and supporting documents

The request for project proposals contains all the details about the project site and its specifications, as well as information on the requirements you must meet as a potential concessionaire and the process for submitting a project proposal.

Proposal on governance regarding the establishment of the SPV for the development and operation of BESS installations in the Port of Antwerp.

Annex 1

2/12/2025
Proposal on governance regarding the establishment of the SPV for the development and operation of BESS installations in the Port of Antwerp.
Download
Stake in to be incorporated SPV for development of BESS-park(s) in the port of Antwerp – RFP.

Request for proposal

2/12/2025
Stake in to be incorporated SPV for development of BESS-park(s) in the port of Antwerp – RFP.
Download

Stay informed about available sites

Sign up and receive a notification as soon as new sites in Antwerp or Zeebrugge come on the market.

Keep me updated
Interesse om te investeren in terreinen bij Port of Antwerp-Bruges

Contact our experts

A
Arno Depover

Program Manager Climate transition

Let’s talk! 

You might also find this interesting