Steenlandlaan

Steenlandlaan gets a much-needed thorough renovation. Works run from 2 March until 19 May.

This had been planned for some time, but was postponed because Steenlandlaan had to serve as a diversion route for the works on the Beveren Tunnel. The renovation is done now because it will coincide with other major road works in the area.

 

During the works, all companies remain accessible.

UPDATE

Phase 2 will not end on 28 March 28, but on 7 April. Phase 3 has started as planned.

Traffic and diversions

For the whole period of the works (2 March – 19 May)

 

  • Through traffic will be diverted via R2 and Beverentunnel.
  • For cyclists (and pedestrians) a passage alongside the works will be guaranteed. Follow the signage on the spot.

Phase 1 of the works is finished.

23 March - 7 April

Phase 2 continues and phase 3 starts. 

 

The diversion for the works between the two roundabouts runs via Land Van Waaslaan and Kruipin.

 

Diversions for:

  • through traffic
  • traffic to and from Haven 1109-1112 (De Rycke, ADPO, WG Aannemingen en Heavy Handling)
  • traffic to and from quays 1103-1107
  • traffic to and from Kallo town centre

Through traffic

3/2/2026

Haven 1109-1112

31/3/2026

Kallo town centre

31/3/2026

Quays 1103-1107

31/3/2026

8 - 19 April

Phase 3 continues.

Diversions for:

  • through traffic
  • traffic to and from Haven 1109-1112 (De Rycke, ADPO, WG Aannemingen en Heavy Handling)
  • traffic to and from quays 1103-1107
  • traffic to and from Kallo town centre

Through traffic

3/2/2026

Haven 1109-1112

1/4/2026

Quays 1103-1107

31/3/2026

Kallo town centre

31/3/2026

20 April - 19 May

Phase 4 of the works is carried out. 

Diversions for:

  • through traffic
  • traffic to and from Haven 1109-1112 (De Rycke, ADPO, WG Aannemingen en Heavy Handling)
  • Kallo town centre

Through traffic

3/2/2026

Haven 1109-1112

30/1/2026

Kallo town centre

30/1/2026